10.85 meter Aluminum Catamaran Progress

Weeks 10 and 11 our factory was closed for the holiday break and we started work again on 9th January 2017. The client has issued a very long list of additional work which will add considerable time to this project. However, progress is good and we are about 75% through the extra work list into Week 14.

alloy catamaran week 14

Window cut-outs are done, handrails complete, radar arch and cover frame on flybridge finished.

Thailand boat builder

Door cut-outs done, aft platform complete.

Mounting for anchor roller and windlass complete.

10.85M Aluminum Fish/Dive Charter Catamaran

Week 9 has now passed and the major fabrication and welding work is finished. The engines have not yet arrived so we have installed the aft topsides and started the long list of small jobs to be completed.

alloy catamaran

Side plating completed

Bow view

Stairs to flybridge

Aluminum catamaran fabrication

Side trim and engine air intake

Flybridge side

Down to forward cabin

Side trim, deck with cleat