10.85 meter Aluminum Catamaran Progress

By February 11, 2017Catamarans
surface drive ubit

Weeks 10 and 11 our factory was closed for the holiday break and we started work again on 9th January 2017. The client has issued a very long list of additional work which will add considerable time to this project. However, progress is good and we are about 75% through the extra work list into Week 14.

alloy catamaran week 14

Window cut-outs are done, handrails complete, radar arch and cover frame on flybridge finished.

Thailand boat builder

Door cut-outs done, aft platform complete.

Mounting for anchor roller and windlass complete.