Week 7 of Pumpkin Island Ferry construction

By | Catamarans

This 11.80 meter aluminum ferry which is being built to Australian government survey NSCV 1D now has the hulls fully plated and 60% of the hull internal welding finished. The first survey inspection was passed two weeks ago and construction is on schedule.aluminum surveyed ferry
Hull plating has proceeded without a hitch and all parts fitted exactly.
ferry for Queensland
We are currently stopped for the annual Songkran festival [Thai New Year] and work will restart on the 20th April 2015.
alloy ferry for Pumpkin Island