Week 9 has now passed and the major fabrication and welding work is finished. The engines have not yet arrived so we have installed the aft topsides and started the long list of small jobs to be completed.
Monthly Archives: December 2016
Week 8 of 10.85 meter Sports Catamaran Build
At the end of week #8 and the cabin exterior, fly bridge and cabin bulkheads have been installed. Interior stairs down to the forward cabin and cabin floor plates are fitted. Almost all interior welding has been completed.