surface drive ubit

10.85 meter Aluminum Catamaran Progress

By | Catamarans

Weeks 10 and 11 our factory was closed for the holiday break and we started work again on 9th January 2017. The client has issued a very long list of additional work which will add considerable time to this project. However, progress is good and we are about 75% through the extra work list into Week 14.

alloy catamaran week 14

Window cut-outs are done, handrails complete, radar arch and cover frame on flybridge finished.

Thailand boat builder

Door cut-outs done, aft platform complete.

Mounting for anchor roller and windlass complete.